STATUS REPORT: ARES-I-X-090409

ARES I-X STATUS REPORT

Launch Vehicle: Ares I-X 
Launch Date: Targeted for Oct. 31 
Launch Pad: 39B at NASA's Kennedy Space Center, Fla. 


Ares I-X Flight Hardware
This week's milestones include:
- Launch Team countdown simulation from the firing room
- First vehicle power up preparations ongoing
- Electrical cable run installations continue in support of power up 

Upcoming milestones: 
- Vehicle power up 

Ares I-X Ground Support Equipment 
- At Launch Pad 39B, modifications are ongoing
- Environmental Control System (ECS) final hardware installations
- Installation of the Vehicle Stabilization System 

The Ares I-X flight test will provide NASA an early opportunity to 
check and prove hardware, analysis and modeling methods, and 
facilities and ground operations needed to develop NASA's next crew 
launch vehicle. 

For more information about the Ares I-X flight test, visit:

http://www.nasa.gov/ares 

Previous status reports are available at:

http://www.nasa.gov/centers/kennedy/moonandmars/status/index.html  

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux