Expendable Launch Vehicle Status Report

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



Feb. 6, 2009

George H. Diller
Kennedy Space Center, Fla.
321-867-2468
george.h.diller@nasa.gov

STATUS REPORT: ELV-020609

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: NOAA-N Prime 
Launch Vehicle: Delta II 7320 
Launch Pad: Space Launch Complex 2, Vandenberg Air Force Base, Calif. 
Launch Date: Feb. 6, 2009 
Launch Time: 2:22 a.m. PST 

The United Launch Alliance Delta II rocket carrying the NOAA-N Prime 
weather satellite launched at 2:22 a.m. PST after two consecutive 
days of launch scrubs. The satellite successfully separated from the 
rocket's second stage 65 minutes after launch. NOAA-N Prime now is in 
its circular polar orbit about 534 miles, or 464 nautical miles, 
above Earth. 



Mission: Orbiting Carbon Observatory (OCO) 
Launch Vehicle: Taurus XL (Orbital Sciences) 
Launch Pad: Space Launch Complex 576-E, Vandenberg Air Force Base, 
Calif. 
Launch Date: Feb. 23, 2009 
Launch Time: 1:51 a.m. PST (7 min., 30 sec. launch window) 

The OCO spacecraft is being mated to the payload attach fitting 
Friday. Encapsulating the spacecraft into the fairing halves begins 
this weekend with the first half on Feb. 7 and the second half on 
Feb. 9. OCO will then go to the launch pad on Feb. 10.

The upper launch vehicle stack, consisting of Taurus stages 1, 2 and 
3, was transported to the launch pad on Feb. 3, joining Stage 0. 
Technicians plan to integrate the encapsulated OCO spacecraft with 
the Taurus third stage on Feb. 13. Finally, the payload/upper launch 
vehicle integrated stack is set to be hoisted atop Stage 0 on Feb. 
16.

Taurus Flight Simulation No. 3 currently is planned for Feb. 11. 



Mission: Kepler 
Launch Vehicle: Delta II 7925 
Launch Pad: 17-B, Cape Canaveral Air Force Station, Fla. 
Launch Date: March 5, 2009 
Launch Time: 10:48:43 p.m. EDT 

Spacecraft fueling operations are set for this weekend. Attaching 
Kepler to the upper stage booster is scheduled for Feb. 16. 
Installing the integrated stack into the transportation canister and 
placing it on the payload transporter are scheduled for the following 
day. Kepler will be moved to Launch Complex 17 on Feb. 19 to be mated 
to the Delta II rocket on Pad 17-B. 



Previous status reports are available at:

http://www.nasa.gov/centers/kennedy/launchingrockets/status/index.html 
 

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux