STATUS REPORT: S-081007

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing 
Status Reports periodically and is the source for information 
regarding processing activities associated with the vehicles and 
payloads.  If you are a member of the media and would like further 
information, visit:  
http://www.nasa.gov/centers/kennedy/news/index.html  


Mission: STS-118 - 22nd International Space Station Flight - S5 Truss 
Segment 
Vehicle: Endeavour (OV-105) 
Official Launch Date: Aug. 8, 2007 
Expected Landing Date: Aug. 19, 2007 
Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Drew
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Today is Flight Day 3 for STS-118. Endeavour is on orbit after 
launching from Pad 39A at KSC at 6:36 p.m. on Aug. 8. On Thursday, 
the crew conducted a photographic survey of the orbiter's thermal 
protection system using the robotic arm and extension boom. Today 
Commander Scott Kelly successfully flipped the orbiter using the 
rendezvous pitch maneuver prior to docking at the International Space 
Station. Docking occurred at 2:02 p.m. EDT. 


Mission: STS-120 - 23rd International Space Station Flight - U.S. Node 
2 
Vehicle: Discovery (OV-103) 
Location: Orbiter Processing Facility Bay 3 
Launch Date: Targeted for Oct. 23, 2007 
Launch Pad: 39A 
Crew: Melroy, Zamka, Parazynski, Wheelock, Wilson, Nespoli and Tani 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

In Orbiter Processing Facility bay No. 3 this week, workers installed 
the right-hand orbital maneuvering system pod and connections are in 
work. Forward, mid-body and aft closeout work continues. Checkout of 
the orbiter's communications system is also in work.

Stacking of the STS-120 solid rocket boosters in the Vehicle Assembly 
Building is complete, and closeout work is under way. 


Mission: STS-122 - 24th International Space Station Flight - Columbus 
Module 
Vehicle: Atlantis (OV-104) 
Location: Orbiter Processing Facility Bay 1 
Launch Date: Targeted for Dec. 6, 2007 
Launch Pad: 39A 
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin and Walheim 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

In Orbiter Processing Bay No. 1, workers are installing new, stronger 
tiles, known as BRI tiles, around the main landing gear doors. 
Hydraulic positioning of the body flap and elevons is complete. The 
main landing gear tires were installed. Removal and replacement of 
fuel cell No. 3 due to abnormal voltage readings is under way.

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux