8-5-02 status

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



KENNEDY SPACE CENTER   
SHUTTLE & PAYLOAD PROCESSING STATUS REPORT  
Monday, August 5, 2002 (1:00 p.m.)

NOTE: This is an orbiter processing report and does not necessarily reflect
the chronological order of upcoming Space Shuttle flights. Visit
http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home
Page for the latest schedule of future Shuttle missions.  


MISSION STS-112 -- 15TH ISS FLIGHT (9A) - BA, ITS S1

VEHICLE: Atlantis/OV-104
LAUNCH DATE: September 28, 2002 NET
MISSION DURATION: 11 days 
CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees

Shuttle Processing Note: Processing continues for Atlantis' launch to the
International Space Station. NASA managers made a decision last week to
perform a welding repair to the cracks in the Main Propulsion System (MPS)
liquid hydrogen flow liners. The welding repairs are scheduled to begin on
Wednesday. In addition to welding, the microscopic rough edges of the liner
holes will be smoothed by polishing to reduce the chance of more cracks
developing in the future.  Following successful welding repairs, engine
installation is scheduled to begin this weekend.

	MISSION: STS-113 - 16th ISS Flight (11A) - ITS, P1


VEHICLE: Endeavour/OV-105
LAUNCH DATE: November 2, 2002 NET
CREW: Wetherbee, Loria, Lopez-Alegria, Herrington; (ISS up) Bowersox,
Budarin, Thomas; (ISS down) Korzun, Whitson, Treschev
ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Processing continues for Endeavour's launch to the
International Space Station. After repairs are completed on Atlantis flow
liners, welders will begin similar repairs on Endeavour. Ammonia servicing
is in work.  Replacement of window No. 8  is complete and leak checks are in
work. 
--more--




MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

VEHICLE - Columbia/OV-102
LAUNCH DATE: November 29, 2002 NET
MISSION DURATION: 16 days
CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon
ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees

Shuttle Processing Note: Nominal processing has been completed in
preparation for Columbia's research mission now scheduled for no earlier
than November 29. Due to the difference in material and number of slots on
Columbia's flow liners, more engineering investigation is needed before a
final repair option is selected.  


ORBITER MAJOR MODIFICATION PERIOD

VEHICLE: Discovery/OV-103

Shuttle Processing Note: Discovery is awaiting the start of its Orbiter
Major Modification (OMM) period that is scheduled to begin at the Kennedy
Space Center late this summer. 

-- end --















-------------------------------------------------------------

For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription.

To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message.

or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/

Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .



[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux