KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Friday, August 2, 2002 (4:30 p.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION STS-112 -- 15TH ISS FLIGHT (9A) - BA, ITS S1 VEHICLE: Atlantis/OV-104 LAUNCH DATE: September 28, 2002 NET MISSION DURATION: 10 days CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees Shuttle Processing Note: Processing continues for Atlantis' launch to the International Space Station. Today, NASA managers made a decision to perform a welding repair to the cracks in the Main Propulsion System (MPS) liquid hydrogen flow liners. The welding repairs are scheduled to begin early next week. In addition to welding, the microscopic rough edges of the liner holes will be smoothed by polishing to reduce the chance of more cracks developing in the future. MISSION: STS-113 - 16th ISS Flight (11A) - ITS, P1 VEHICLE: Endeavour/OV-105 LAUNCH DATE: November 2, 2002 NET CREW: Wetherbee, Loria, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Thomas; (ISS down) Korzun, Whitson, Treschev ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Processing continues for Endeavour's launch to the International Space Station. After repairs are completed on Atlantis flow liners, welders will begin similar repairs on Endeavour. Ammonia servicing and replacement of window No. 2 are in work. MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION VEHICLE - Columbia/OV-102 LAUNCH DATE: November 29, 2002 NET MISSION DURATION: 16 days CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees Shuttle Processing Note: Nominal processing has been completed in preparation for Columbia's research mission now scheduled for no earlier than November 29. Due to the difference in material and number of slots on Columbia's flow liners, more engineering investigation is needed before a final repair option is selected. ORBITER MAJOR MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: Discovery is awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. -- end -- ------------------------------------------------------------- For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message. or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/ Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .