Calligra Plan: Schedule Overbooking

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



Hi all, 

I'm just getting my feet wet with Calligra Plan, and I'm liking it so far. Kudos to the devs! I've got a question on the Schedule calculation though, and I'm hoping someone out there can give me a nudge in the right direction. I created a resource-loaded schedule with one Resource, then I made a new Schedule, and I chose "Avoid" for the "Overbooking" field, then I click "Calculate." 

When I go to the "Resource Assignments (Gantt)" view, hough, my one resource nevertheless appears to be overbooked (i.e. there are sequences of red blocks in the Gantt chart for that Resource and the stacked assignments exceed availability of the resource in those periods), and the project certainly fits well within the stated start and end dates of the main project. So i can't imagine that the overbooking is really "unavoidable." Any suggestions on what I might be doing wrong here or misunderstanding? 

FWIW my system config is:
Ubuntu 14.04LTS x64
Plan Version 2.8.1 
Using KDE Development Platform 4.13.3
[Installed via Synaptic Package Manager]

Kind Regards,
Vic
___________________________________________________
This message is from the kde mailing list.
Account management:  https://mail.kde.org/mailman/listinfo/kde.
Archives: http://lists.kde.org/.
More info: http://www.kde.org/faq.html.

[Index of Archives]     [Trinity (TDE) Desktop Users]     [Fedora KDE]     [Fedora Desktop]     [Linux Kernel]     [Gimp]     [GIMP for Windows]     [Gnome]     [Yosemite Hiking]
  Powered by Linux