On 11/25/2016 05:51 PM, Peter Robinson wrote:
So we already do pretty much what you outline above. I started the
first push to f25-updates on the Friday before the release.
I think, we are talking past each other.
You seem to be referring to "the freeze" in terms of the final release
push, while I am talking about what you'd probably call alpha or beta stage.
Actually, I am referring to the stage of the release preparations, when
rel-eng stops pushing packages from "update-testing" to "main".
This stage, in case of f25, has taken ca. 3-4 weeks (IIRC).
During this stage, many fc25 updates stalled in updates-testing, while
their fc23/fc24/rawhide counterparts had been pushed into "main" =>
broken update paths.
Ralf
_______________________________________________
devel mailing list -- devel@xxxxxxxxxxxxxxxxxxxxxxx
To unsubscribe send an email to devel-leave@xxxxxxxxxxxxxxxxxxxxxxx