SF Gate: BART's airport service in limbo/How soon trial run can begin is unclear

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



=20
----------------------------------------------------------------------
This article was sent to you by someone who found it on SF Gate.
The original article can be found on SFGate.com here:
http://www.sfgate.com/cgi-bin/article.cgi?file=3D/chronicle/archive/2003/02=
/16/BA238489.DTL
----------------------------------------------------------------------
Sunday, February 16, 2003 (SF Chronicle)
BART's airport service in limbo/How soon trial run can begin is unclear
Michael Cabanatuan, Chronicle Staff Writer


   San Francisco -- Don't pack the suitcases and head to BART to start that
vacation just yet. It could be months more before the long-awaited
extension to San Francisco International Airport opens.
   Contractor Tutor-Saliba/Slattery, which was supposed to wrap up
construction in early November, still hasn't turned over the project to
BART so that testing of the $1.5 billion extension can begin.
   "Every week, we wonder: Is it this week?" said Molly MacArthur, a BART
spokeswoman for the extension project. "We don't have any expectation of
when it's going to be turned over, but we are anxious."
   The 8.7-mile, four-station extension from Colma has already sped past ma=
ny
deadlines. When BART broke ground in November 1997, officials predicted
that the first train would roll into SFO's international terminal by the
end of 2001. Then weather and an endangered snake that was crushed at a
construction site combined to push the deadline back to late fall 2002.
   But in July 2002, BART officials admitted they wouldn't finish in time f=
or
the holidays and predicted a January opening.
   Last month, they admitted they wouldn't meet that deadline.
   Tired of announcing opening dates and then having to retract them, BART
officials have stopped making projections until they take possession of
the extension and can begin two to three months of testing.
   BART riders appear to be as eager for the extension as the officials.
Several have called or e-mailed The Chronicle wondering whether it's going
to be completed in time for their spring or summer trips out of SFO.
   "I left California about a year ago and they were talking about an openi=
ng
date then," said Matthew Ko, an electrical engineer from Richland, Wash.,
who often flies into SFO to visit his family in Davis. "It seems silly to
me that it's taking so long to open it up."
   Under the best of circumstances -- which would include a contractor
turnover this week -- the earliest BART could run its first train full of
passengers into SFO's international terminal would be around the end of
April. But sources at BART say privately that a May opening seems more
likely.
   Ron Tutor, Tutor-Saliba president, did not return messages left at his
Sylmar (Los Angeles County) office by The Chronicle on Friday. But BART
spokesman Mike Healy said Tutor has assured BART officials that the
turnover will come "very soon."
   In an interview last month, Tutor cited "some minor difficulties in
control and testing," but no major problems. A $65,000-a-day fine has been
piling up since the company missed the November deadline -- although BART
and Tutor- Saliba will arrive at a settlement that takes into account who
was responsible for which delays.
   BART officials say there's no specific station or system that's holding =
up
the turnover and final testing -- just a lot of little things.
   "It's kind of a checklist of a bunch of various items," said BART's Heal=
y.
   That includes certifications for elevators at the Millbrae station,
completing fare-gate installation at the SFO station and testing
escalators, he said.
   Tutor-Saliba is obligated to turn over "a complete and working system,"
said MacArthur. BART inspectors have gone over the system and identified
problems that need to be fixed, she said, likening the process to a walk-
through inspection on a new house.
   "It's our last chance to make sure everything is done," MacArthur said.
"You don't want to accept anything until you are sure it's done and
working the way you want it to be."
   Both BART and Tutor-Saliba are testing components of the extension, but
once the transit agency takes possession, it will begin eight to 12 weeks
of integrated tests, in which it makes sure everything works together and
in concert with the rest of the system.
   During those tests, BART will operate the extension as if it were in
service -- running trains on a schedule, running escalators and elevators,
and testing the signs, the automated announcement system and the links
with BART's Oakland control center.
   "We're going to make sure everything is operating in tiptop shape before
we begin service," said Healy.
   Ko can hardly wait.
   "It's going to be great," he said. "It's going to be so convenient."

   E-mail Michael Cabanatuan at mcabanatuan@sfchronicle.com.=20
----------------------------------------------------------------------
Copyright 2003 SF Chronicle

[Index of Archives]         [NTSB]     [NASA KSC]     [Yosemite]     [Steve's Art]     [Deep Creek Hot Springs]     [NTSB]     [STB]     [Share Photos]     [Yosemite Campsites]