On Wednesday 10 February 2016 05:41 PM,
Ani Peter wrote:
We discussed on this topic during G11N FAD [1] as a F24 planning and came up with following dates. * 2016-03-01 Alpha Release * 2016-03-03 Software L10N QA Test day * 2016-03-15 Software Translation Deadline * 2016-03-21 Software I18N QA Test day But number of things change after it. Most important schedule is delayed by 3 weeks already. Just adding 3 weeks in earlier planned date, how about 24th March (Thursday)? Created ticket for planning [2]. Lets list down task need to accomplish prior test day. Thanks, Pravin Satpute 1. https://docs.google.com/document/d/17LU-PmtuirbGd7wfxUuKTz7X6fsv82PVPgZaDELi4js/ 2. https://fedorahosted.org/G11N/ticket/18 |
_______________________________________________ g11n mailing list g11n@xxxxxxxxxxxxxxxxxxxxxxx http://lists.fedoraproject.org/admin/lists/g11n@xxxxxxxxxxxxxxxxxxxxxxx