Date: October 21, 2009 8:52:59 PM PDT
Subject: Reversing flow of WAL shipping
Hey Folks,
I want to run a warm standby scenario by you. I'm pretty sure it'll
work, but it's a very large database so even the slightest mistake can
mean a major setback.
Scenario:
Server A is the provider node, shipping WAL files to Server B. Server
B is destined to become the provider node (newer hardware), and has a
sibling Server C that will be the warm standby.
Here's the question: when I turn Server B into the production/provider
node, it's going to switch into the next timeline. If I then attempt
to put Server A (or Server C) into recovery mode, will it switch to
the new current timeline, or complain about being in the older
timeline? Do I have to take another full backup of Server B after
it's become the production/provider node?
Thanks,
David