Expendable Launch Vehicle Status Report

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



Sept. 18, 2009

George H. Diller
Kennedy Space Center, Fla.
321-867-2468
george.h.diller@nasa.gov

STATUS REPORT: ELV-091809

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Space Tracking and Surveillance System - Demonstrators 
Program (STSS-Demo) 
Launch Vehicle: Delta II 7920-10 
Launch Pad: Launch Pad 17-B, Cape Canaveral Air Force Station, Fla. 
Launch Date: No earlier than Sept. 23, 2009 
Launch Window: 8 - 9 a.m. EDT 

To accommodate readiness of the STSS Demo spacecraft, the launch of 
the Delta II has been rescheduled for no earlier than Wednesday, 
Sept. 23 at 8 a.m. EDT. The launch window is 60 minutes in duration.

Loading of the hypergolic propellants aboard the Delta II second stage 
is scheduled for Sept. 20. The mission countdown dress rehearsal will 
also be performed that day. The Launch Readiness Review is to be held 
on Sept. 21. 

On Sept. 22 at 11:30 p.m., the mobile service tower will be pulled 
away from the Delta II rocket. On launch day, Sept. 23, the terminal 
countdown begins at 5:20 a.m. to start the loading of the RP-1 fuel 
and liquid oxygen aboard the Delta II first stage. 

At this time there is a 40 percent probability of not meeting the 
launch weather criteria during the one hour launch opportunity. 



Spacecraft: Wide-field Infrared Survey Explorer (WISE) 
Launch Vehicle: Delta II 7320 
Launch Pad: SLC-2, Vandenberg Air Force Base, Calif. 
Launch Date: Dec. 7, 2009 
Launch Window: 9:10 - 9:23 a.m. EST 

At the Astrotech payload processing facility on north Vandenberg, WISE 
spacecraft testing continues. This week the Mission Sequence Test and 
Operational Readiness Test are under way and will conclude next week. 


Build-up of the Delta II at Space Launch Complex 2 is scheduled to 
begin on Oct. 19 with hoisting of the first stage into the launcher. 



Spacecraft: Solar Dynamics Observatory (SDO) 
Launch Vehicle: Atlas V-401 
Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla. 
Launch Date: Feb. 3, 2010 
Launch Window: 10:53 - 11:53 a.m. EST 

With the launch being rescheduled to Feb. 3, 2010 the SDO spacecraft 
is in a dwell period at Astrotech. There is no testing or processing 
activity currently under way. Spacecraft launch preparations are 
currently planned to resume on Sept. 28. 



Previous status reports are available at:

http://www.nasa.gov/centers/kennedy/launchingrockets/status/index.html 
 

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux