ARES I-X STATUS REPORT

Launch Vehicle: Ares I-X 
Launch Date: Targeted for no earlier than August 30 
Launch Pad: 39B at NASA's Kennedy Space Center, Fla. 


Ares I-X Flight Hardware

This week's milestones include:

- Super Stack 1 assembly is now complete with the attaching of the 
forward assembly to the fifth segment simulator. Stack one is made up 
of eight individual pieces: interstages 1 and 2, the frustum, the 
forward skirt extension, the forward skirt and the aft, center and 
forward segments of the fifth segment simulator. It also includes two 
internal elements, the roll control system and the first stage 
avionics module.

- The aft assembly, which comprises the aft skirt and aft motor 
segment, was moved from the Rotation Processing and Surge Facility to 
the Vehicle Assembly Building. It was lifted onto the Mobile Launcher 
Platform in High Bay 3, signifying the beginning of stacking 
operations.

- The aft center motor segment also was moved from the Rotation 
Processing and Surge Facility to the Vehicle Assembly Building and 
attached to the aft assembly in High Bay 3.

- Camera installed on the upper stage simulator

Last week milestones completed include:

- Aft assembly closeouts

- VAB High Bay 3 stacking preparations 

Next processing milestones:

- Instrumentation testing

- Stack 1 modal test

A series of sensors strategically located throughout the stack will 
measure the amount and direction of movement, as the 
electro-mechanical shakers impose random loads to determine the 
rocket segment's first several bending modes. A comparison will be 
made between predicted and measured mode shapes to verify the flight 
dynamics model. 

- Forward center motor segment stacking

Ares I-X Ground Support Equipment

- At Launch Pad 39B, modification are ongoing.


The gaseous vent arm, beanie cap and orbiter access arm have been 
removed. The vehicle stabilization system is being built at the base 
of the launch pad. The Ares I-X flight test will provide NASA an 
early opportunity to check and prove hardware, analysis and modeling 
methods, and facilities and ground operations needed to develop the 
Ares I, which is NASA's next crew launch vehicle. The test also will 
allow NASA to gather critical data during the ascent of the 
integrated stack, which will help inform the design of the Ares I 
rocket and the Orion crew exploration vehicle. The data will ensure 
the entire vehicle system is safe and fully operational before 
astronauts begin traveling in it to the International Space Station 
and moon. 

For more information about the Ares I-X flight test, visit:

http://www.nasa.gov/ares 

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux