STATUS REPORT: ELV-061209

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Lunar Reconnaissance Orbiter/Lunar Crater Observation and 
Sensing Satellite (LRO/LCROSS) 
Launch Vehicle: Atlas V 
Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla. 
Launch Date: June 17, 2009 
Launch Time: 3:51 p.m. EDT 

The Flight Readiness Review for LRO/LCROSS was held on June 10, and at 
its conclusion, there were no issues or concerns which would preclude 
a launch next week on June 17.

On June 11, a mission dress rehearsal was conducted. This was a 
high-fidelity exercise for the launch team and affirmed their 
readiness for the countdown.

The Atlas V and LRO/LCROSS have been undergoing prelaunch preparations 
in the Vertical Integration Facility adjacent to the launch pad. The 
spacecraft closeouts for flight were completed on June 10.

In preparation for launch, the Atlas V launch vehicle with LRO/LCROSS 
atop is scheduled to be rolled out to the pad on June 16 at 10 a.m. 
The countdown on launch day, June 17, will start at 8:41 a.m. for a 
liftoff targeted to occur at 3:51 p.m. 



Mission: Geostationary Operational Environmental Satellite (GOES-O) 
Launch Vehicle: Delta IV 
Launch Pad: Launch Complex 37, Cape Canaveral Air Force Station, Fla. 
Launch Date: June 26, 2009 
Launch Window: 6:14 - 7:14 p.m. EDT 

At the Astrotech Space Operations Facility on June 7, GOES-O enclosed 
in the payload fairing was rolled out of its payload processing 
facility high bay and moved to Launch Complex 37. It arrived at the 
launch pad on June 8 and was hoisted for mating atop the Delta IV 
rocket during the overnight hours of June 9. The Interface 
Verification Test to verify the electrical and mechanical connections 
between GOES-O and the Delta IV was conducted on June 10. The Flight 
Program Verification, an integrated countdown and powered flight 
electrical test involving both the Delta IV and GOES-O, was 
successfully conducted on June 11.

Also on June 10, the launch vehicle's linear shape charge, part of the 
flight termination system, successfully completed its testing.

NASA has contracted with Boeing to build and launch the GOES-O 
spacecraft. The NASA Launch Services Program at Kennedy is supporting 
the launch in an advisory role. NASA spacecraft project management 
for GOES-O is the responsibility of NASA's Goddard Space Flight 
Center. After launch, once Boeing and NASA have completed on-orbit 
checkout and the spacecraft is operational, it will be turned over to 
NOAA. 



Previous status reports are available at:

http://www.nasa.gov/centers/kennedy/launchingrockets/status/index.html 
 

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux