Expendable Launch Vehicle Status Report

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



May 30, 2008

George H. Diller
Kennedy Space Center, Fla.
321-867-2468
george.h.diller@nasa.gov

STATUS REPORT: ELV-053008

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: GLAST (Gamma-ray Large Area Space Telescope) 
Launch Vehicle: Delta II 7920-H (United Launch Alliance) 
Launch Pad: 17-B 
Launch Date: June 5, 2008 
Launch Window: 11:45 a.m. - 1:40 p.m. EDT 

The launch of NASA's GLAST spacecraft aboard a United Launch Alliance 
Delta II rocket is being scheduled for Thursday, June 5, instead of 
no earlier than June 3. The launch window extends from 11:45 a.m. to 
1:40 p.m. EDT and remains unchanged through Aug. 7.

The June 5 date is already reserved for the launch of GLAST on the 
Eastern Range. The decision was made at the conclusion of Thursday's 
Flight Readiness Review to give the launch team sufficient time to 
determine that remaining open engineering issues are resolved.

Loading of the hypergolic propellants into the Delta II second stage 
is scheduled for Monday, June 2. On launch day, June 5, the mobile 
service tower will be retracted from around the rocket at 2 a.m. 
Loading of the liquid oxygen to begin the final phase of the launch 
countdown will begin at 10 a.m. which will lead to a liftoff targeted 
for 11:45 a.m. EDT. 

Mission: OSTM/Jason-2 
Location: Astrotech payload processing facility, Vandenberg Air Force 
Base 
Launch Vehicle: Delta II 7320 (United Launch Alliance) 
Launch Pad: Space Launch Complex 2, Vandenberg Air Force Base 
Launch Date: June 15, 2008 
Launch Window: 1:47 - 1:56 a.m. PDT 

At the Astrotech payload processing facility on north Vandenberg, the 
spacecraft has been mated to the Delta II payload attach fitting, and 
spacecraft closeouts have been completed. On Sunday, June 1, 
OSTM/Jason-2 will be installed into the payload transportation 
canister. The following day, June 2, it will be moved to Space Launch 
Complex 2 to be mated with the Delta II rocket.

The Flight Program Verification, an integrated test of both the Delta 
II and the OSTM/Jason-2 spacecraft, will be conducted on June 5. This 
is the last major test before launch. The payload fairing will be 
installed around the spacecraft on June 9. The Delta II second stage 
hypergolic propellants will be loaded into the vehicle on June 12. 

Previous status reports are available at:

http://www.nasa.gov/centers/kennedy/launchingrockets/status/2008 

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux