NASA's Space Shuttle Processing Status Report

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



Nov. 21, 2007

Candrea Thomas
Kennedy Space Center, Fla.
321-867-2468
candrea.k.thomas@nasa.gov

STATUS REPORT: S-112107

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing 
Status Reports periodically and is the source for information 
regarding processing activities associated with the vehicles and 
payloads.  If you are a member of the media and would like further 
information, visit:  
http://www.nasa.gov/centers/kennedy/news/index.html  


Mission: STS-122 - 24th International Space Station Flight - Columbus 
Module 
Vehicle: Atlantis (OV-104) 
Location: Launch Pad 39A 
Launch Date: Targeted for Dec. 6, 2007 
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Last weekend, engineers and technicians successfully resolved an issue 
with a stuck valve in Atlantis' forward reaction control system, 
isolating the problem to a broken ground lug in the helium isolation 
valve circuit. Repairs were made and the valve is now functioning 
normally. Throughout the week, workers continued to validate 
shuttle/pad connections, and orbiter aft closeout work begins Nov. 
28. Because no major issues are being worked and processing has been 
going well, teams will have Thanksgiving Day through Sunday off.

On Saturday, Nov. 17, the STS-122 crew arrived at Kennedy Space Center 
for the terminal countdown demonstration test, or TCDT, which 
included a countdown dress rehearsal and a training exercise. The 
crew returned to NASA's Johnson Space Center Tuesday following the 
TCDT's successful conclusion. 


Mission: STS-123 - 25th International Space Station Flight - Kibo, 
Dextre 
Vehicle: Endeavour (OV-105) 
Location: Orbiter Processing Facility Bay 2 
Launch Date: Targeted for Feb. 14, 2008 
Launch Pad: 39A 
Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

In Orbiter Processing Facility bay No. 2, integrated testing of the 
main engines and the main propulsion system continues. Testing of the 
orbiter's three-string GPS system, which provides guidance on 
re-entry, is complete.

The star tracker door functional test is complete. Window No. 7 has 
been removed and replaced. The payload bay door functional test is 
finished. Installation of BRI tile around the perimeter of the right 
main landing gear door is finished. Checkout of the Shuttle to 
Station Power Transfer System is complete.

In high bay No. 1 of the Vehicle Assembly Building, stacking of the 
left solid rocket booster is under way. Stacking of the right booster 
is scheduled to begin next week. 


Mission: STS-124 - 26th International Space Station Flight - Kibo 
Pressurized Module, Japanese Remote Manipulator System 
Vehicle: Discovery (OV-103) 
Location: Orbiter Processing Facility Bay 3 
Launch Date: Targeted for April 24, 2008 
Launch Pad: 39A 
Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

In Orbiter Processing Facility bay No. 3, hypergolic fuel has been 
off-loaded from the orbital maneuvering system. Inspections of the 
reinforced carbon-carbon panels on the wing leading edges are 
complete. The main engine dome heat shields have been removed, and 
preparations are under way for removal of the three main engines next 
week. Functional checkout of the forward reaction control system is 
in progress, and window No. 1 has been removed and replaced. 
Post-flight inspection of the thermal protection system is 70 percent 
complete.

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux