03.09.07

Jessica Rye
Kennedy Space Center, Fla.
321-867-2468

STATUS REPORT: S-030907

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing 
Status Reports periodically and is the source for information 
regarding processing activities associated with the vehicles and 
payloads.  If you are a member of the media and would like further 
information, visit:  
http://www.nasa.gov/centers/kennedy/news/index.html  

Mission: STS-117 - 21st International Space Station Flight (13A) - 
S3/S4 Truss Segment Solar Arrays 
Vehicle: Atlantis (OV-104) 
Location: Vehicle Assembly Building 
Launch Date: Targeted for April 2007 
Launch Pad: 39A 
Crew: Sturckow, Archambault, Reilly, Swanson, Forrester and Olivas 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

On Sunday, Atlantis rolled from Launch Pad 39A to the Vehicle Assembly 
Building, where employees spent the week positioning platforms around 
the shuttle to allow for inspections and repairs to hail-damaged 
areas. Inspections of the external tank are expected to be completed 
next week. Some foam sanding has begun in the nose cone area of the 
tank.

Inspections are finished for the solid rocket boosters and nearly 
complete for the orbiter, with 20 of 28 hail-damaged areas, all on 
the left side of the vehicle, already repaired. 


Mission: STS-118 - 22nd International Space Station Flight (13A.1) - 
S5 Truss Segment 
Vehicle: Endeavour (OV-105) 
Location: Orbiter Processing Facility Bay 2 
Launch Date: Targeted for June 28, 2007 
Launch Pad: 39A 
Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and 
Anderson 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Endeavour remains in Orbiter Processing Facility bay 2, and 
technicians continue preparing the vehicle for its first launch in 
more than four years. The vehicle has undergone an extensive 
modification period, including the addition of all of the 
return-to-flight safety upgrades added to both Discovery and 
Atlantis. 

This week, technicians successfully completed fuel cell No. 2 coolant 
loop reservicing. The payload premate testing is under way. Checkout 
and interface verification for the orbital maneuvering system and the 
forward reaction control system was completed. Hydraulic 
system/flight control system checkout has concluded. The thermal 
barriers of the nose landing gear door are being installed prior to 
the landing gear functional test. 


Mission: STS-122 - 24th International Space Station Flight (1E) - 
Columbus Laboratory 
Vehicle: Discovery (OV-103) 
Location: Orbiter Processing Facility Bay 3 
Launch Date: Targeted for Fall 2007 
Launch Pad: TBD 
Crew: Frick, Poindexter, Walheim, Love, Melvin, Schlegel and Eyharts 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Processing of Discovery, which returned from the STS-116 mission on 
Dec. 22, continues in Orbiter Processing Facility bay 3. 

Technicians are busy working on Discovery's electrical system, 
preparing for the installation of the new Station to Shuttle Power 
Transfer System modification. This system will allow the orbiter and 
International Space Station to share power, which will enable the 
orbiter to remain docked for longer periods of time. Work is also 
under way to replace thermal tile around the main landing gear door 
and the external tank doors with a stronger tile, known as BRI tile. 
Water spray boiler No. 1 installation was completed, and main 
propulsion system flow liner inspections are under way.

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux