NASA SPACE SHUTTLE DISCOVERY'S LAUNCH COUNTDOWN BEGINS JUNE 28

NASA will begin the countdown for the launch of Space Shuttle 
Discovery at 5 p.m. EDT June 28, at the T-43 hour point. The 
countdown includes nearly 28 hours of built-in hold time leading to a 
preferred launch time at about 3:49 p.m. EDT on July 1. The launch 
window extends for about five minutes.

The Kennedy Space Center launch team will conduct the countdown from 
the newly renovated Firing Room 4 of the Launch Control Center. 

This mission is the 115th shuttle flight and the 18th U.S. flight to 
the International Space Station. Discovery's mission, designated 
STS-121, is scheduled to last about 12 days with a planned landing at 
about 10:45 a.m. EDT on July 13 at Kennedy. The STS-121 crew will 
test new equipment and procedures to improve shuttle safety, as well 
as deliver supplies and make repairs to the International Space 
Station. 

Discovery rolled into Kennedy's Orbiter Processing Facility on Aug. 22 
last year, after returning from its last mission, STS-114. On May 12, 
the shuttle rolled out of the facility and into the Vehicle Assembly 
Building, where it was mated to its redesigned external fuel tank and 
solid rocket boosters. The space shuttle stack was transferred to 
Launch Pad 39B on May 19.

The STS-121 crew includes Commander Steven Lindsey, Pilot Mark Kelly 
and mission specialists Michael Fossum, Lisa Nowak, Stephanie Wilson, 
Piers Sellers and Thomas Reiter, an astronaut with the European Space 
Agency. Reiter will join the Expedition 13 crew on the station as 
flight engineer 2 and will become the first long-duration crew member 
who is not American or Russian.

The STS-121 mission is the second mission in the Return to Flight 
sequence. Payloads aboard Discovery include a new control and 
life-support system that uses water to generate enough oxygen for up 
to six people. Science experiments requiring data collection from 
crew members will help understand space motion sickness, latent virus 
reactivation and shedding, renal stone formation and insomnia.

In the payload bay, the multi-purpose logistics module Leonardo, built 
by the Italian Space Agency, will carry more than two tons of 
hardware, equipment and supplies up to the station and return 
unneeded items back to Earth. This is Leonardo's fourth trip to the 
station.

During two planned spacewalks on the fifth and seventh days of the 
mission, Sellers and Fossum will test the 50-foot robotic arm boom 
extension as a work platform and also test techniques for inspecting 
and repairing the reinforced carbon-carbon segments that protect the 
shuttle's nose cone and wing leading edges. The spacewalkers will 
install spare parts for future use and replace the trailing umbilical 
system reel assembly for the station's mobile transporter, a rail car 
that travels along the station's truss.

COUNTDOWN MILESTONES 
*Televised events (times may vary slightly)
All times Eastern

Launch-3 Days (Wednesday, June 28)

Prepare for the start of the STS-121 launch countdown
Perform the call-to-stations (4:30 p.m.)
Countdown begins at the T-43 hour mark (5 p.m.)
Begin final vehicle and facility close-outs for launch
Check out backup flight systems
Review flight software stored in mass memory units and display systems
Load backup flight system software into Discovery's general-purpose 
computers

Launch-2 Days (Thursday, June 29)

Remove mid-deck and flight-deck platforms (1 a.m.)
Complete preparation to load power reactant storage and distribution 
system (4 a.m.)
Activate and test navigational systems (6 a.m.)
Flight deck preliminary inspections complete (9 a.m.)

Enter first built-in hold at T-27 hours for duration of 4 hours (9 
a.m.)

Clear launch pad of all non-essential personnel
Perform test of the vehicle's pyrotechnic initiator controllers

Resume countdown (1 p.m.)

Begin operations to load cryogenic reactants into Discovery's fuel 
cell storage tanks (2:30 p.m.)

Enter 4-hour built-in hold at T-19 hours (9 p.m.)

Demate orbiter mid-body umbilical unit (9:30 p.m.)
Resume orbiter and ground support equipment closeouts

Launch-1 Day (Friday, June 30)

Resume countdown (1 a.m.)

Final preparations of shuttle's three main engines for main propellant 
tanking and flight (1 a.m.)
Begin filling pad sound suppression system water tank (2 a.m.)
Pad sound suppression system water tank filling complete (5 a.m.)
Close out the tail service masts on the mobile launcher platform

Enter planned hold at T-11 hours for 13 hours, 53 minutes (9 a.m.)

Begin star tracker functional checks (9:50 a.m.)
Activate orbiter's inertial measurement units
Activate the orbiter's communications systems 
Install film in numerous cameras on the launch pad (10:55 a.m.)
Flight crew equipment late stow (2:50 p.m.)
Move Rotating Service Structure (RSS) to the park position (6:30 p.m.)
Perform ascent switch list
Fuel cell flow-through purge complete

Resume countdown at T-11 hours (10:53 p.m.)

Launch Day (Saturday, July 1)

Activate the orbiter's fuel cells (12:02 a.m.)
Clear the blast danger area of all non-essential personnel
Switch Discovery's purge air to gaseous nitrogen (12:53 a.m.)

Enter planned 2-hour built-in hold at the T-6 hour mark (3:53 a.m.)

Launch team verifies no violations of launch commit criteria prior to 
cryogenic loading of the external tank
Clear pad of all personnel

Resume countdown (5:53 a.m.)

Chill down of propellant transfer lines (5:53 a.m.)
Begin loading the external tank with about 500,000 gallons of 
cryogenic propellants (about 6:03 a.m.)
Complete filling the external tank with its flight load of liquid 
hydrogen and liquid oxygen propellants (about 8:53 a.m.)
Final Inspection Team proceed to launch pad

Enter planned 3-hour built-in hold at T-3 hours (8:53 a.m.)

Perform inertial measurement unit preflight calibration
Align Merritt Island Launch Area (MILA) tracking antennas
Perform open loop test with Eastern Range

Resume countdown at T-3 hours (11:53 a.m.)

Crew departs Operations and Checkout Building for the pad (11:58 a.m.)
Complete closeout preparations in the white room
Check cockpit switch configurations 
Flight crew begins entry into the orbiter (about 12:28 p.m.)
Astronauts perform air-to-ground voice checks with Launch and Mission 
Control
Begin to close Discovery's crew hatch (about 1:38 p.m.)
Begin Eastern Range final network open loop command checks
Perform hatch seal and cabin leak checks
Complete white room closeout 
Closeout crew moves to fallback area
Primary ascent guidance data is transferred to the backup flight 
system

Enter planned 10-minute hold at T-20 minutes (2:33 p.m.)

NASA test director conducts final launch team briefings
Complete inertial measurement unit preflight alignments

Resume countdown at T-20 minutes (2:43 p.m.)

Transition the orbiter's onboard computers to launch configuration 
Start fuel cell thermal conditioning
Close orbiter cabin vent valves
Transition backup flight system to launch configuration

Enter estimated 40-minute hold at T-9 minutes (2:54 p.m.)

Launch director, mission management team and NASA test director 
conduct final polls for go/no go to launch

Resume countdown at T-9 minutes (about 3:40 p.m.)

Start automatic ground launch sequencer (T-9:00 minutes)
Retract orbiter crew access arm (T-7:30)
Start mission recorders (T-6:15)
Start Auxiliary Power Units (T-5:00)
Arm SRB and ET range safety safe and arm devices (T-5:00)
Start liquid oxygen drainback (T-4:55)
Start orbiter aerosurface profile test (T-3:55)
Start main engine gimbal profile test (T-3:30)
Pressurize liquid oxygen tank (T-2:55)
Begin retraction of the gaseous oxygen vent arm (T-2:55)
Fuel cells to internal reactants (T-2:35)
Pressurize liquid hydrogen tank (T-1:57)
Deactivate bi-pod heaters (T-1:52)
Deactivate SRB joint heaters (T-0:60 seconds)
Orbiter transfers from ground to internal power (T-0:50 seconds)
Ground Launch Sequencer go for auto sequence start (T-0:31 seconds)
SRB gimbal profile (T-0:21 seconds)
Ignition of three space shuttle main engines (T-6.6 seconds)
SRB ignition and liftoff (T-0)

CREW FOR MISSION STS-121
Commander (CDR): Steven Lindsey 
Pilot (PLT): Mark Kelly 
Mission Specialist (MS1): Michael Fossum 
Mission Specialist (MS2): Lisa Nowak
Mission Specialist (MS3): Stephanie Wilson
Mission Specialist (MS4): Piers Sellers
Mission Specialist (MS5): Thomas Reiter 

SUMMARY OF STS-121 LAUNCH DAY CREW ACTIVITIES

Saturday, July 1
5:15 a.m. - Crew wakes up
*10:10 a.m. - Crew Photo opportunity
10:48 a.m. - Weather briefing (CDR, PLT, MS2)
*11:30 a.m. - Astronauts put on flight suits
*11:58 a.m. - Depart for launch pad
*12:28 p.m. - Arrive at white room and begin to enter Discovery
*1:43 p.m. - Close crew hatch
*3:49 p.m. - Launch 

For information about the STS-121 crew and its mission to the 
International Space Station, visit:

http://www.nasa.gov/shuttle

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux