NASA's Space Shuttle Processing Status Report

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



12.02.05

J.D. Harrington
Headquarters, Washington
Phone: (202) 358-5241

Jessica Rye
Kennedy Space Center, Fla.
Phone: (321) 867-2468

STATUS REPORT: S-120205

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing 
Status Reports each week, and is the source for information regarding 
processing activities associated with the vehicles and payloads. This 
report does not necessarily reflect the chronological order of future 
Space Shuttle missions. If you are a member of the media and would 
like further information, visit 
http://www.nasa.gov/centers/kennedy/news/index.html. 

Discovery (OV-103)

Mission: STS-121 - 18th International Space Station Flight (ULF1.1) 
Payload: Multi-Purpose Logistics Module 
Location: Orbiter Processing Facility Bay 3 
Launch Date: TBD - No earlier than May 2006 
Launch Pad: 39B 
Crew: Lindsey, Kelly, Sellers, Fossum, Nowak, Wilson and Reiter 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Technicians continue to process Discovery for NASA's second shuttle 
return-to-flight test mission, STS-121. Powered-up system testing and 
drag chute door installation continue. Once the cure on the door is 
complete, it will be opened to verify proper cure, and the flight 
pins will be installed. 

The orbiter boom sensor system is in the transfer aisle of the 
processing facility awaiting installation. Final work will be 
completed soon on the manipulator positioning mechanism, the 
pedestals that hold the boom in place in the payload bay, and the 
boom will be installed next week. 

Atlantis (OV-104)

Mission: STS-115 - 19th International Space Station Flight (12A) 
Payload: P3/P4 Solar Arrays 
Location: Orbiter Processing Facility Bay 1 
Launch Date: TBD 
Launch Pad: 39B 
Crew: Jett, Ferguson, Tanner, Burbank, MacLean and Stefanyshyn-Piper 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Atlantis processing continues on schedule. Thermal protection system 
gap-filler pull tests are complete. Work will begin soon to replace 
selected gap fillers identified during pull tests and analysis. This 
work is being performed due to two gap fillers that protruded from 
the underside of Discovery during STS-114. New installation 
procedures are being developed to ensure the gap fillers stay in 
place and do not pose a hazard during re-entry.

Preparations to install the forward reaction control system continue. 
The cavity closeout photos were completed Thursday, and the 
installation of the system is scheduled for early next week. This 
control system provides the thrust for attitude maneuvers, pitch, yaw 
and roll, and for small velocity changes along the orbiter axis. 

Endeavour (OV-105)

Body-flap power drive-unit installation continues in Orbiter 
Processing Facility Bay 2, with work focused on safety wire and 
insulation. The main landing gear was cycled this week to support 
environmental seal compression testing on compartment doors. The 
vehicle will remain powered down for work on the new modification, 
called the "station to shuttle power transfer system." The system 
will allow the shuttle to remain docked to the station longer. 

External Tank

At NASA's Michoud Assembly Facility in New Orleans, engineers continue 
evaluating the causes of the foam loss during Discovery's launch in 
July. Detailed inspections of the Protuberance Air Load ramp of 
external tank #120 show at least one crack that extends all the way 
to the tank's base foam layer. Evaluation continues on the cracks, 
their cause and the possibility of flying STS-121 without the ramp. 

Preliminary analysis indicates it is aerodynamically feasible, but 
additional wind-tunnel testing will be scheduled to ensure flight 
integrity. Work continues to meet a May launch window. If additional 
testing shows the ramp is needed, external tank processing will be 
stopped until requirements are assessed. 

Previous Space Shuttle processing status reports are available on the 
Internet at: 

http://www.nasa.gov/shuttle



For information about NASA and agency programs on the Internet, visit: 




http://www.nasa.gov/

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux