Space Shuttle Processing Status Report

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



03.25.05

Jessica Rye
Kennedy Space Center, Fla.
(321) 867-6185 

STATUS REPORT: S2-12

SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing 
Status Reports each week, and is the source for information regarding 
processing activities associated with the vehicles and payloads. This 
report does not necessarily reflect the chronological order of future 
Space Shuttle missions. If you are a member of the media and would 
like further information, visit 
http://www.nasa.gov/centers/kennedy/news/index.html. 

Mission: STS-114 - 17th ISS Flight (LF1) - Multi-Purpose Logistics 
Module 
Vehicle: Discovery (OV-103) 
Location: Orbiter Processing Facility Bay 3 
Launch Date: Launch Planning Window May 15 - June 3, 2005 
Launch Pad: 39B 
Crew: Collins, Kelly, Noguchi, Robinson, Thomas, Lawrence and Camarda 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Technicians in Orbiter Processing Facility bay 3 make final 
preparations for Discovery's rollover to the Vehicle Assembly 
Building (VAB) on Monday, March 28. The work is completed in the 
payload bay on the fasteners in the wire trays that were causing 
minor chafing on the tubing surrounding the wires. The wire tray 
covers were removed, the chafe protection added, and then borescope 
inspections were performed to ensure there was clearance between the 
fasteners and the wires.

The payload bay doors were closed today, following payload bay 
cleaning, final radiator inspections and completion of closeout 
photography. The payload bay doors will be reopened at the launch pad 
for the installation of the payload, the Italian-built Multi-Purpose 
Logistics Module (MPLM) Raffaello.

Discovery will be powered down tomorrow in preparation for its 
rollover. The aft area of the vehicle where the Space Shuttle Main 
Engines and Main Propulsion System are located is closed out for 
flight. Over the weekend, technicians will remove the ground support 
equipment stands from the vehicle and take final vehicle weight and 
center of gravity measurements. Discovery will be loaded on the 
Orbiter Transporter System on Sunday.

Once Discovery arrives in the VAB, a sling will lift and lower the 
vehicle between its twin Solid Rocket Boosters and Discovery will be 
mated, or attached, to its redesigned External Tank. Once mated, the 
fully assembled Space Shuttle stack will undergo final closeouts 
including installation of the new digital camera in the orbiter, 
electrical and mechanical attachments, umbilical checks, and the 
interface verification test.

In the Space Station Processing Facility, cargo stowage installation 
into the MPLM Raffaello continues in preparation for MPLM hatch 
closure scheduled for mid-April. Raffaello will carry supplies such 
as food, clothing and spare parts to the International Space Station. 
The STS-114 crew participated in the Payload Crew Equipment Interface 
Test on March 18. The crew performed equipment interface fit checks 
of the Thermal Protection System repair sample box, the Control 
Moment Gyroscope and the External Stowage Platform-2 in preparation 
for the mission's three scheduled spacewalks. The crew also inspected 
the resupply stowage containers installed in Raffaello. 

Mission: STS-121 - 18th ISS Flight (ULF1) - Multi-Purpose Logistics 
Module 
Vehicle: Atlantis (OV-104) 
Location: Orbiter Processing Facility Bay 1 
Launch Date: Launch Planning Window July 12 - July 31, 2005 
Launch Pad: 39B 
Crew: Lindsey, Kelly, Sellers, Fossum, Nowak and Wilson 
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles 

Technicians continue work in OPF bay 1 for Atlantis' mission, 
designated STS-121, to the International Space Station. On orbiter 
Endeavour, wiring was found in a cable tray in the payload bay that 
showed the fasteners were causing minor chafing on the tubing 
surrounding the wires. Rework on Discovery is complete and borescope 
inspections of wire trays on Atlantis continue.

Atlantis' new Orbiter Boom Sensor System (OBSS) arrived at Kennedy 
Space Center last week and was transported to the Remote Manipulator 
System lab in the VAB for checkout and final testing before 
installation in the vehicle. The boom is scheduled to arrive in the 
bay on April 4 for installation on April 6. The four Manipulator 
Positioning Mechanisms that will hold Atlantis' OBSS on the starboard 
side of the payload bay are installed. The 50-foot-long OBSS will 
attach to the Remote Manipulator System, or Shuttle robotic arm, and 
is one of the new safety measures for Return to Flight, equipping the 
orbiter with cameras and laser systems to inspect the Shuttle's 
Thermal Protection System while in space.

Next week Solid Rocket Booster (SRB) stacking will begin for Atlantis' 
launch. The right aft booster is scheduled to be moved from the 
Rotation Processing and Surge Facility to the VAB and lifted onto the 
Mobile Launch Platform. The External Tank (ET) remains in the 
checkout cell for final testing. Following the completion of SRB 
stacking, the ET will be moved and attached to the SRBs in late 
April. 

Endeavour (OV-105) 

Endeavour is in its Orbiter Major Modification period, which began in 
December 2003.

Previous Space Shuttle processing status reports are available on the 
Internet at: 

http://www.nasa.gov/returntoflight

	
-end-



To subscribe to the list, send a message to: 
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux