Kennedy Space Center Newsletter

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



12.10.04
Jessica Rye
 Kennedy Space Center, Fla.
 (321) 867-6185
STATUS REPORT: S1-37

SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports each week, and is 
the source for information regarding processing activities associated with the vehicles and 
payloads. This report does not necessarily reflect the chronological order of future Space Shuttle 
missions. If you are a member of the media and would like further information, visit 
http://www.nasa.gov/centers/kennedy/news/index.html

 Discovery (OV-103)

 In the Orbiter Processing Facility (OPF), orbiter powered-system testing continues for Discovery's 
Return to Flight mission, designated STS-114, to the International Space Station. Auxiliary Power 
Unit water servicing and leak check sample results are complete. The three Space Shuttle Main 
Engines were moved from the Main Engine Shop and installed on Discovery for flight. Engines were 
installed in positions No. 1 and 3 on Wednesday, with No. 2 completed on Thursday. 

 Engine installation was scheduled to begin on Monday, but was delayed due to an issue with the 
vehicle used to install the engines. During the installation of Space Shuttle Main Engine 2057 into 
engine position No. 1 on Discovery, the engine shifted to the right, allowing the low-pressure fuel 
duct on the engine to touch a Thermal Protection System tile on the right Orbiter Maneuvering 
System (OMS) pod. There was no damage to the engine or the OMS pod and the tile will be repaired in 
place. There will be no impact to the milestone for Return to Flight. 

 Atlantis (OV-104)

 Technicians continue to process Atlantis in the Orbiter Processing Facility for its mission to the 
International Space Station. The orbiter continues to remain in a power-down period to complete the 
final wiring for the Return to Flight modifications, including the new Orbiter Boom Sensor System, 
wing leading edge sensors and the External Tank separation camera. 

 Following the installation of all four Rudder Speed Brake (RSB) actuators last week, technicians 
installed the panels and right-hand shafts, with the left-hand shafts being installed today. 

 Endeavour (OV-105)

 Space Shuttle Endeavour is in its Orbiter Major Modification period, which began in December 2003. 
Electrical modifications continue in the crew module. Three-String Global Positioning System wire 
routing in the avionics bay and flight deck continues. 

 Following the removal of miniscule corrosion, the right-hand wing leading edge was painted and the 
left wing is scheduled to be painted this weekend. The External Tank door installation is complete 
in preparation for roll-over to the Vehicle Assembly Building next week, clearing the bay for a 
scheduled maintenance period. 

	
-end-



To subscribe to the list, send a message to: ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to: ksc-unsubscribe@newsletters.nasa.gov

[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux