SHUTTLE MISSION STS-107 LAUNCH TIME ANNOUNCED FOR LAUNCH ON JAN. 16

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



NASA News 
National Aeronautics and
Space Administration

John F. Kennedy Space Center
Kennedy Space Center, Florida 32899
AC 321-867-2468
____________________________________________________________________________
_______________________________
For Release: Jan. 15, 2003 

KSC Contact: Bruce Buckingham				
(321) 867-2468						
	
KSC Release No. 09 - 03

SHUTTLE MISSION STS-107 LAUNCH TIME ANNOUNCED FOR LAUNCH ON JAN. 16

Managers today confirmed the launch of Space Shuttle Columbia for Thursday,
Jan. 16 at 10:39 a.m. EST. The launch window extends for 2 hours and 30
minutes. This announcement comes following a final review of Shuttle
processing activities and a satisfactory engineering analysis of the Ball
Strut Tie Rod Assembly (BSTRA).

STS-107 is a scheduled 16-day mission with a planned KSC landing at about
8:53 a.m. EST on Saturday, Feb. 1.

This mission is the first Shuttle mission of 2003. Mission STS-107 is the
28th flight of the orbiter Columbia and the 113th flight overall in NASA's
Space Shuttle program. 

Mission STS-107 is an international mission devoted to space research, the
first dedicated research mission to be flown by the Shuttle in almost three
years. Columbia will carry in its payload bay the SPACEHAB Research Double
Module, a pressurized environment accessible to the crew. The module and the
Shuttle's middeck will hold most of the mission's more than 80 experiments -
involving more than 70 scientists worldwide - that will investigate space,
life and physical sciences.

The STS-107 crew includes Commander Rick Husband, Pilot William McCool,
Mission Specialists David Brown, Laurel Clark, Kalpana Chawla and Michael
Anderson, and Payload Specialist Ilan Ramon with the Israel Space Agency. 

(end of general release)

REMAINING COUNTDOWN MILESTONES
*all times are Eastern

Launch-1 Day (Wednesday, Jan. 15)
(As of 11 a.m. EST, the countdown clock is in a scheduled built-in hold at
the T-11 hour mark) 

	*	Flight crew equipment late stow
	*	Move Rotating Service Structure (RSS) to the park position
(about 4 p.m.)
	*	Perform ascent switch list
	*	Fuel cell flow-through purge complete

Resume countdown at T-11 hours (8:19 p.m.)

	*	Activate the orbiter's fuel cells (9:34 p.m.)
	*	Clear the blast danger area of all nonessential personnel
	*	Switch Columbia's purge air to gaseous nitrogen (10:19 p.m.)

Launch Day (Thursday, Jan. 16)

Enter planned 1-hour built-in hold at the T-6 hour mark (1:19 a.m.)

	*	Launch team verifies no violations of launch commit criteria
prior to cryogenic loading of the external tank 
	*	Clear pad of all personnel
	*	Begin loading the external tank with about 500,000 gallons
of cryogenic propellants (as early as 1:49 a.m.)

Resume countdown at T-6 hours (2:19 a.m.)

	*	Complete filling the external tank with its flight load of
liquid hydrogen and liquid oxygen propellants (about 4:49 a.m.)
	*	Final Inspection Team proceed to launch pad

Enter planned 2-hour built-in hold at T-3 hours (5:19 a.m.)

	*	Perform inertial measurement unit preflight calibration
	*	Align Merritt Island Launch Area (MILA) tracking antennas
	*	Perform open loop test with Eastern Range

Resume countdown at T-3 hours (7:19 a.m.)

	*	Complete close-out preparations in the white room
	*	Check cockpit switch configurations 
	*	Begin Eastern Range final network open loop command checks
	*	Primary ascent guidance data is transferred to the backup
flight system
	*	Complete inertial measurement unit preflight alignments
	
Enter planned 10-minute hold at T-20 minutes (9:59 a.m.)

	*	NASA Test Director conducts final launch team briefings
	*	Transition the orbiter's onboard computers to launch
configuration 
	*	Start fuel cell thermal conditioning
	*	Close orbiter cabin vent valves
	*	Transition backup flight system to launch configuration

Resume countdown at T-20 minutes (10:09 a.m.)

Enter estimated 10-minute hold at T-9 minutes (10:20 a.m.)

	*	Launch Director, Mission Management Team and NASA Test
Director conduct final polls for go/no go to launch

Resume countdown at T-9 minutes (about 10:30 a.m.)

	*	Start automatic ground launch sequencer (T-9:00 minutes)
	*	Retract orbiter crew access arm (T-7:30)
	*	Start mission recorders (T-6:15)
	*	Start Auxiliary Power Units (T-5:00)
	*	Arm SRB and ET range safety safe and arm devices (T-5:00)
	*	Start liquid oxygen drainback (T-4:55)
	*	Start orbiter aerosurface profile test (T-3:55)
	*	Start main engine gimbal profile test (T-3:30)
	*	Pressurize liquid oxygen tank (T-2:55)
	*	Begin retraction of the gaseous oxygen vent arm (T-2:55)
	*	Fuel cells to internal reactants (T-2:35)
	*	Pressurize liquid hydrogen tank (T-1:57)
	*	Deactivate SRB joint heaters (T-1:00)
	*	Orbiter transfers from ground to internal power (T-0:50
seconds)
	*	Ground Launch Sequencer go for auto sequence start (T-0:31
seconds)
	*	SRB gimbal profile (T-0:21 seconds)
	*	Ignition of three Space Shuttle main engines (T-6.6 seconds)
	*	SRB ignition and liftoff (T-0) 


-- end--



-------------------------------------------------------------

For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription.

To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message.

or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/

Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .



[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux