KENNEDY SPACE CENTER
SHUTTLE & PAYLOAD PROCESSING STATUS REPORT  
Monday, October 28, 2002 (1:00 p.m.)

For the latest Shuttle status on the web visit
http://www-pao.ksc.nasa.gov/kscpao/status/stsstat/current.htm <http://www
pao.ksc.nasa.gov/kscpao/status/stsstat/current.htm>. 
Visit <http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm>  for the
latest schedule of future Shuttle missions.  KSC press releases can be found
at <http://www-pao.ksc.nasa.gov/kscpao/release/release.htm>.  The KSC home
page can be found at <http://www.ksc.nasa.gov/>. 


	MISSION: STS-113 - 16th ISS Flight (11A) - P1 Truss Segment

VEHICLE: ENDEAVOUR/OV-105
TARGET LAUNCH DATE: Nov. 10, 2002 
TARGET LAUNCH TIME:  12:00 a.m. - 4: 00 a.m. 
TARGET LANDING DATE:  Nov. 20, 2002 
MISSION DURATION: 11 days 
CREW: Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox,
Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev 
ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles /51.6 degrees

Shuttle Processing Note:  Space Shuttle Endeavour is at Launch Pad 39-A
preparing for its lift off to the International Space Station next month.
Hypergolic propellant loading is complete and aft closeouts are in work.
Tomorrow technicians will perform a check out of the spacesuits.  The Flight
Readiness Review is scheduled for Thursday at KSC. Following this meeting, a
firm launch date is expected to be announced.


MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

VEHICLE - Columbia/OV-102
TARGET LAUNCH DATE: Jan. 16, 2003 NET
TARGET LANDING DATE: Feb. 1, 2003
MISSION DURATION: 16 days
CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon
ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees

Shuttle Processing Note:  Columbia continues processing in preparation for
its research mission scheduled for no earlier than Jan. 16.  Engine
installation and leak checks are complete and heat shield installation is in
work.  


MISSION STS-114 -- 17TH ISS FLIGHT (UFL1) - CREW ROTATION/MULTI-PURPOSE
LOGISTICS MODULE

VEHICLE: Atlantis/OV-104
TARGET LAUNCH DATE: March 1, 2003 
TARGET LANDING DATE: March 12, 2003 
MISSION DURATION: 11 days 
SHUTTLE CREW:  Collins, Kelly, Noguchi, Robinson
ISS EXPEDITION CREW 7:  Malenchenko, Moschenko, Lu
ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees

Shuttle Processing Note:  Post-flight inspections from STS-112 continue in
preparation for STS-114, scheduled to launch early next year. Heat shields
have been removed with engine removal scheduled for Tuesday.

ORBITER MAJOR MODIFICATION PERIOD

VEHICLE: Discovery/OV-103

Shuttle Processing Note: The Orbiter Major Modification (OMM) period for
Discovery continues with wire inspections in the crew module this week. 


-- end --







-------------------------------------------------------------

For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription.

To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message.

or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/

Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .



[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux