9-3-02 STATUS

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



KENNEDY SPACE CENTER   
SHUTTLE & PAYLOAD PROCESSING STATUS REPORT  
Tuesday, September 3, 2002 (1:30 p.m.)

NOTE: This is an orbiter processing report and does not necessarily reflect
the chronological order of upcoming Space Shuttle flights. Visit
http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home
Page for the latest schedule of future Shuttle missions.  


MISSION STS-112 -- 15TH ISS FLIGHT (9A) - BA, ITS S1

VEHICLE: Atlantis/OV-104
TARGET LAUNCH DATE: Oct. 2, 2002 NET
TARGET LAUNCH PERIOD: 2 - 6 p.m.
TARGET LANDING DATE: Oct. 13, 2002 
MISSION DURATION: 11 days 
CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees

Shuttle Processing Note: Nominal processing continues for Atlantis' launch
to the International Space Station now scheduled for no earlier than Oct. 2.
The orbiter is currently installed on the Orbiter Transporter in preparation
for its move to be stacked with the Solid Rocket Boosters and External Tank.
Over the weekend, technicians noted a concern in the mid-body regarding
movement of the Manipulator Positioning Mechanism that is attached to the
Remote Manipulator System in the payload bay. Engineers are reviewing the
information to determine a resolution and if additional work will be
necessary.
Technicians have removed and replaced all of the 32 bearings located in the
JEL (jacking, equalization and leveling) cylinders and reinstalled the 16
cylinders on Crawler Transporter No. 2.  The retest is scheduled for late
this week.

	MISSION: STS-113 - 16th ISS Flight (11A) - ITS, P1


VEHICLE: Endeavour/OV-105
TARGET LAUNCH DATE: Nov. 2, 2002 NET
TARGET LANDING DATE: TBD
MISSION DURATION: 11 days
CREW: Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox,
Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev
ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Endeavour continues processing for its upcoming
launch to the International Space Station. Remote Manipulator System
checkout is complete.  Main Propulsion System leak checks and ammonia
servicing are in work. 


MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

VEHICLE - Columbia/OV-102
TARGET LAUNCH DATE: Jan. 16, 2003 NET
TARGET LANDING DATE: Jan. 27, 2003
MISSION DURATION: 16 days
CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon
ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees

Shuttle Processing Note: Nominal processing has been completed in
preparation for Columbia's research mission now scheduled for no earlier
than Jan. 16. 


ORBITER MAJOR MODIFICATION PERIOD

VEHICLE: Discovery/OV-103

Shuttle Processing Note: The Orbiter Major Modification (OMM) period for
Discovery is underway with radiator removal and nose landing gear
retraction. Wire inspections will be performed throughout the entire vehicle
during the OMM and began in the crew compartment this week. 

-- end --















-------------------------------------------------------------

For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription.

To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message.

or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/

Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .



[Index of Archives]     [KSC Site]     [NASA News]     [NASA Science News]     [JPL]     [Marshall Space Flight Center]     [NTSB]     [Yosemite News]     [Tuolumne Meadows Campground]     [STB]     [Deep Creek Forum]     [Cassini Status Reports]     [Telescopes]

  Powered by Linux