KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Tuesday, September 3, 2002 (1:30 p.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION STS-112 -- 15TH ISS FLIGHT (9A) - BA, ITS S1 VEHICLE: Atlantis/OV-104 TARGET LAUNCH DATE: Oct. 2, 2002 NET TARGET LAUNCH PERIOD: 2 - 6 p.m. TARGET LANDING DATE: Oct. 13, 2002 MISSION DURATION: 11 days CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees Shuttle Processing Note: Nominal processing continues for Atlantis' launch to the International Space Station now scheduled for no earlier than Oct. 2. The orbiter is currently installed on the Orbiter Transporter in preparation for its move to be stacked with the Solid Rocket Boosters and External Tank. Over the weekend, technicians noted a concern in the mid-body regarding movement of the Manipulator Positioning Mechanism that is attached to the Remote Manipulator System in the payload bay. Engineers are reviewing the information to determine a resolution and if additional work will be necessary. Technicians have removed and replaced all of the 32 bearings located in the JEL (jacking, equalization and leveling) cylinders and reinstalled the 16 cylinders on Crawler Transporter No. 2. The retest is scheduled for late this week. MISSION: STS-113 - 16th ISS Flight (11A) - ITS, P1 VEHICLE: Endeavour/OV-105 TARGET LAUNCH DATE: Nov. 2, 2002 NET TARGET LANDING DATE: TBD MISSION DURATION: 11 days CREW: Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Endeavour continues processing for its upcoming launch to the International Space Station. Remote Manipulator System checkout is complete. Main Propulsion System leak checks and ammonia servicing are in work. MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION VEHICLE - Columbia/OV-102 TARGET LAUNCH DATE: Jan. 16, 2003 NET TARGET LANDING DATE: Jan. 27, 2003 MISSION DURATION: 16 days CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees Shuttle Processing Note: Nominal processing has been completed in preparation for Columbia's research mission now scheduled for no earlier than Jan. 16. ORBITER MAJOR MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: The Orbiter Major Modification (OMM) period for Discovery is underway with radiator removal and nose landing gear retraction. Wire inspections will be performed throughout the entire vehicle during the OMM and began in the crew compartment this week. -- end -- ------------------------------------------------------------- For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message. or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/ Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .