KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Monday, August 19, 2002 (10:30 a.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION STS-112 -- 15TH ISS FLIGHT (9A) - BA, ITS S1 VEHICLE: Atlantis/OV-104 TARGET LAUNCH DATE: Sept. 28, 2002 NET TARGET LANDING DATE: Oct. 9, 2002 MISSION DURATION: 11 days CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees Shuttle Processing Note: Processing continues for the STS-112 launch to the International Space Station. All three of Atlantis' main engines have been installed. Main propulsion system leak checks and heat shield installation are in work. Engineering evaluation continues on the cracks found in the bearings located in the JEL (jacking, equalization and leveling) cylinders on Crawler Transporter No. 2. Technicians have removed eight of the 16 cylinders on Crawler No.2 to perform visual inspection of the bearings, while managers assess possible options for repair. MISSION: STS-113 - 16th ISS Flight (11A) - ITS, P1 VEHICLE: Endeavour/OV-105 TARGET LAUNCH DATE: Nov. 2, 2002 NET TARGET LANDING DATE: Nov. 13, 2002 MISSION DURATION: 11 days CREW: Wetherbee, Loria, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Processing continues for Endeavour's launch to the International Space Station. Technicians completed polishing of the downstream Main Propulsion System flow liner slots on Endeavour and will continue the work on the upstream liners today. Welding of the cracks found in the liners is scheduled to begin as early as this afternoon. MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION VEHICLE - Columbia/OV-102 TARGET LAUNCH DATE: Nov. 29, 2002 NET TARGET LANDING DATE: Dec. 15, 2002 MISSION DURATION: 16 days CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees Shuttle Processing Note: Nominal processing has been completed in preparation for Columbia's research mission now scheduled for no earlier than Nov. 29. ORBITER MAJOR MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: Discovery is awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. -- end -- ------------------------------------------------------------- For automatic email subscriptions to this KSC originated press releases, send an Internet electronic mail message to mailto:ksc-news_release-subscribe@kscnews.ksc.nasa.gov. With no subject or message. The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an email addressed to mailto:ksc-news_release-unsubscribe@kscnews.ksc.nasa.gov . With no subject or message. or you can (un)subscribe on the World Wide Web at: http://kscnews.ksc.nasa.gov/ Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm .