As brick-mux tests were failing (and still are on master), this was holding up the release activity. We now have a final fix [1] for the problem, and the situation has improved over a series of fixes and reverts on the 4.1 branch as well. So we hope to branch RC0 today, and give a week for package and upgrade testing, before getting to GA. The revised calendar stands as follows, - RC0 Tagging: 31st May, 2018 - RC0 Builds: 1st June, 2018 - June 4th-8th: RC0 testing - June 8th: GA readiness callout - June 11th: GA tagging - +2-4 days release announcement Thanks, Shyam [1] Last fix for mux (and non-mux related): https://review.gluster.org/#/c/20109/1 On 05/09/2018 03:41 PM, Shyam Ranganathan wrote: > Here is the current release activity calendar, > > - RC0 tagging: May 14th > - RC0 builds: May 15th > - May 15th - 25th > - Upgrade testing > - General testing and feedback period > - (on need basis) RC1 build: May 26th > - GA readiness call out: May, 28th > - GA tagging: May, 30th > - +2-4 days release announcement > > Thanks, > Shyam > > On 05/06/2018 09:20 AM, Shyam Ranganathan wrote: >> Hi, >> >> Release 4.1 has been branched, as it was done later than anticipated the >> calendar of tasks below would be reworked accordingly this week and >> posted to the lists. >> >> Thanks, >> Shyam >> >> On 03/27/2018 02:59 PM, Shyam Ranganathan wrote: >>> Hi, >>> >>> As we have completed potential scope for 4.1 release (reflected here [1] >>> and also here [2]), it's time to talk about the schedule. >>> >>> - Branching date (and hence feature exception date): Apr 16th >>> - Week of Apr 16th release notes updated for all features in the release >>> - RC0 tagging: Apr 23rd >>> - Week of Apr 23rd, upgrade and other testing >>> - RCNext: May 7th (if critical failures, or exception features arrive late) >>> - RCNext: May 21st >>> - Week of May 21st, final upgrade and testing >>> - GA readiness call out: May, 28th >>> - GA tagging: May, 30th >>> - +2-4 days release announcement >>> >>> and, review focus. As in older releases, I am starring reviews that are >>> submitted against features, this should help if you are looking to help >>> accelerate feature commits for the release (IOW, this list is the watch >>> list for reviews). This can be found handy here [3]. >>> >>> So, branching is in about 4 weeks! >>> >>> Thanks, >>> Shyam >>> >>> [1] Issues marked against release 4.1: >>> https://github.com/gluster/glusterfs/milestone/5 >>> >>> [2] github project lane for 4.1: >>> https://github.com/gluster/glusterfs/projects/1#column-1075416 >>> >>> [3] Review focus dashboard: >>> https://review.gluster.org/#/q/starredby:srangana%2540redhat.com >>> _______________________________________________ >>> maintainers mailing list >>> maintainers@xxxxxxxxxxx >>> http://lists.gluster.org/mailman/listinfo/maintainers >>> >> _______________________________________________ >> maintainers mailing list >> maintainers@xxxxxxxxxxx >> http://lists.gluster.org/mailman/listinfo/maintainers >> > _______________________________________________ > Gluster-devel mailing list > Gluster-devel@xxxxxxxxxxx > http://lists.gluster.org/mailman/listinfo/gluster-devel > _______________________________________________ Gluster-devel mailing list Gluster-devel@xxxxxxxxxxx http://lists.gluster.org/mailman/listinfo/gluster-devel