On Fri, 2009-07-24 at 10:13 -0400, Bill Nottingham wrote: > Mark McLoughlin (markmc@xxxxxxxxxx) said: > > > http://poelstra.fedorapeople.org/schedules/f-12/f-12-releng-tasks.html > > > http://poelstra.fedorapeople.org/schedules/f-12/f-12-releng.ics > > > > In the F-11 schedule, we had 85 days between Feature Freeze and GA. And > > then GA slipped by two weeks. > > > > In the F-12 schedule, we now have 99 days between Feature Freeze and GA. > > > > This seriously cuts into development time, and we already have a shorter > > releases cycle. > > > > Why is that? > > At least one week of this (that I recall) is to have the feature freeze > be a week before the 'code freeze' for the milestone; the idea is that > to avoid the 'all features land at once, and we have to spend a week > cleaning them up' problem. Had that last time too: http://fedoraproject.org/wiki/Releases/11/Schedule 2009-03-03 Feature Freeze 2009-03-10 Beta Freeze Cheers, Mark. -- fedora-devel-list mailing list fedora-devel-list@xxxxxxxxxx https://www.redhat.com/mailman/listinfo/fedora-devel-list