I did this, but with the benefit of taking the network with me, just a forklift from one datacenter to the next. Shutdown the clients, then OSDs, then MDS/MON/MGRs, then switches. Reverse order back up, > On Jan 28, 2020, at 4:19 AM, Marc Roos <M.Roos@xxxxxxxxxxxxxxxxx> wrote: > > > Say one is forced to move a production cluster (4 nodes) to a different > datacenter. What options do I have, other than just turning it off at > the old location and on on the new location? > > Maybe buying some extra nodes, and move one node at a time? > > > _______________________________________________ > ceph-users mailing list -- ceph-users@xxxxxxx > To unsubscribe send an email to ceph-users-leave@xxxxxxx
Attachment:
smime.p7s
Description: S/MIME cryptographic signature
_______________________________________________ ceph-users mailing list -- ceph-users@xxxxxxx To unsubscribe send an email to ceph-users-leave@xxxxxxx