hammer timing

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

 



Things were pretty slow over the holidays, so here's the current plan.

- Extend the current sprint (v0.92) until the end of this week (1/11).  
At that time the already-frozen v0.91 will get released and v0.92 will 
freeze.

- Do one more two week sprint (v0.93) from 1/12 to 1/25.  v0.92 will 
release and v0.93 will freeze.  This will effectively be the feature 
freeze for hammer.

- Two weeks after that we'll release v0.93, the first hammer release 
candidate.

- Hopefully two weeks after that v0.94 (final hammer) will follow.  This 
will depend on how things look stability-wise, though; we may want to do a 
second release candidate and make v0.95 hammer final.

Sound okay?
sage

--
To unsubscribe from this list: send the line "unsubscribe ceph-devel" in
the body of a message to majordomo@xxxxxxxxxxxxxxx
More majordomo info at  http://vger.kernel.org/majordomo-info.html



[Index of Archives]     [CEPH Users]     [Ceph Large]     [Information on CEPH]     [Linux BTRFS]     [Linux USB Devel]     [Video for Linux]     [Linux Audio Users]     [Yosemite News]     [Linux Kernel]     [Linux SCSI]
  Powered by Linux