Tuesday, December 11, 2007 (AP)
Boeing Says Latest 787 Schedule on Track
By DAVE CARPENTER, AP Business Writer


   (12-11) 09:28 PST Chicago (AP) --

   Boeing Co. said Tuesday that its schedule for the 787 Dreamliner remains
on track and it does not currently envision further delays in the
much-ballyhooed airplane.

   Officials of the aerospace company reaffirmed the latest schedule in a
conference call updating the 787 program's status, two months after it
pushed back flight testing and initial deliveries of the aircraft by six
months.

   Many industry observers ultimately anticipate additional delays, which a=
re
common with new airplanes.

   Scott Carson, head of Boeing's Seattle-based commercial airplane
manufacturing division, acknowledged the company still is "ironing out
significant supply-chain wrinkles" but said there are no revisions to the
latest schedule.

   "The plan we announced in October for the 787 is unchanged: to fly the
first airplane around the end of the first quarter of 2008 and begin
deliveries in late November or December timeframe, and to deliver 109
airplanes in 2009," Carson said. "That is our team's commitment, and we
intend to perform to that commitment."

   The first flight test had been scheduled for early fall.

   The 787, Boeing's first newly designed jet since airlines started flying
the 777 in 1995, will be the world's first large commercial airplane made
mostly of carbon-fiber composites, which are lighter, more durable and
less prone to corrosion than more traditional aluminum. Boeing says it
will be cheaper to maintain and offer better fuel efficiency and more
passenger comforts than comparable planes flying today.

   But the unprecedented plan to assemble a jet from components manufactured
largely by other companies ran into early snags when the outsourcing led
to a variety of problems involving contractors in numerous countries. It
also was dogged by shortages of fasteners and other small parts that hold
large sections of the plane together.

   Pat Shanahan, who replaced Mike Bair as vice president and general manag=
er
of the Everett, Wash.-based 787 program in October as a result of the
production problems, said Boeing is "making progress against our plans."
He said parts shortages are declining and availability of fasteners has
improved, enabling installation work to accelerate.

   But he appeared to leave the door open to a potential scaling back in the
target of delivering 109 airplanes by the end of 2009 if everything
doesn't go smoothly in the interim.

   "There's no doubt our ramp-up is aggressive, but throughout this effort =
we
have not found any fundamental flaws in our production system design that
would lead me to believe it's not doable," Shanahan said.

   "The key will be our ability and that of our partners to work through the
front-end production issues and meet the component delivery schedules into
final assembly. And of course the plan assumes no major unknowns are
uncovered in flight test."

   The program chief said the 787 team is applying more detailed processes
than before and systematically working through the details of its
challenges, such as mapping every open hole and fastener. Previously, he
said, it had been "trying to brute-force through some of these obstacles
thinking that they would break through more quickly."

   Boeing has solved the "big problems" but remains frustrated by small
details in the process, Shanahan said.

   A key to meeting the timetable will come in late January when it complet=
es
remaining installation work and turns the aircraft's power on.

   "Our schedule becomes much more predictable once we get the power on
because the airplane is finally in the state that our factory was designed
for," Shanahan said. "Once we have power on, we can perform basic
integrated functional testing and then transition to" remaining testing,
he said.

   The delay highlights inherent problems in building new airplanes and ris=
ks
slowing the momentum Boeing built up after years of lagging behind
European rival Airbus, which itself stumbled in introducing its superjumbo
A380 two years behind schedule.

   It also has hurt the company's credibility on updates like the one made
Tuesday, according to Lehman Brothers analyst Joseph Campbell.

   "Because Boeing insisted there would be no 787 delay until well after mo=
st
observers had concluded that a delay was certain, we think what Boeing
says going forward carries less weight than it did a year ago," he said in
an investor report issued Monday. "Unfortunately, no one, including it
appears Boeing, really knows how the 787 program certification, production
ramp-up and Boeing profit recognition will go."

   Boeing shares, which topped $107 before the six-month delay was announced
in October, fell $1.10 to $91.54 in afternoon trading.

   ___

   On the Net:

   www.boeing.com ---------------------------------------------------------=
-------------
Copyright 2007 AP

<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<<>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

If you wish to unsubscribe from the AIRLINE List, please send an E-mail to:
"listserv@xxxxxxxxxxxxxxxxx".  Within the body of the text, only write the following:"SIGNOFF AIRLINE".

[Index of Archives]         [NTSB]     [NASA KSC]     [Yosemite]     [Steve's Art]     [Deep Creek Hot Springs]     [NTSB]     [STB]     [Share Photos]     [Yosemite Campsites]