Published Monday, March 15, 2004, in the Los Angeles Times

Alterations to LAX Plan May Not Fly

Time constraints and legal issues complicate the City Council's
ability to change the $9-billion proposal.  Critics say it may need
modification.

By Jennifer Oldham

Six months before the City Council gets its say on Mayor James
K. Hahn's $9-billion plan to modernize Los Angeles International
Airport, some legal experts are arguing that time constraints and
strict environmental laws will prevent the council from altering the
proposal.

If the council makes significant changes, according to this line of
thinking, it might send airport officials back to the drawing board
and jeopardize the nine years and $123 million the city has already
spent to devise a politically palatable LAX plan.

Not everybody at City Hall agrees with this analysis.  In particular,
Councilwoman Cindy Miscikowski, whose district includes LAX and who
has been critical of Hahn's plan, said she believes that the council
can and should amend the proposal.

And legal experts hired by several industries who are opposed to
Hahn's plan say the notion that policymakers' hands will be tied by
the time they review the proposal contradicts the very point of the
deliberate public review process.

"The thing that's important is to allow for public agencies to respond
to public comments by making modifications in the project," said
Barbara Higgins, a Los Angeles attorney who represents the Los Angeles
Airlines Airport Affairs Committee, a group of airlines that carry
almost half the passenger traffic at LAX.  "Otherwise, the whole
public review process would be meaningless."

The dispute has emerged as Hahn's LAX plan enters a crucial phase.
Airport officials will finish incorporating 3,200 public comments
into the proposal in the next several weeks.  The 31-volume report is
scheduled to make its way through numerous city and county agencies
this year on a tight timeline that calls for council approval by
Sept. 14.

In the meantime, airport-area residents, the airlines and several
influential local and federal lawmakers have called on Hahn to make
significant changes, including scrapping a controversial new passenger
check-in center near the San Diego Freeway, abandoning a plan to
demolish Terminals 1, 2 and 3, and revising the construction schedule.

But Hahn's advisors say that making changes of that magnitude would
stall the massive public works project.  An army of consultants has
already spent 36 months devising the mayor's LAX plan.

"You can't just simply add a program, or subtract a program, or
reschedule it without it having potential implications for each of
the different elements you're looking at," said Steve Rosenthal, a
Washington, D.C., attorney who advises the city.

Hahn has refused to revise his plan before it's considered by the
council."The mayor feels that the plan should be considered as a whole
program," said Shannon Murphy, a spokeswoman for Hahn.  "It identifies
specific impacts and mitigations.  We feel that significant changes to
the plan may imperil its validity."

Hahn's plan would dramatically alter the way travelers arrive at and
use LAX.  Private vehicles would be rerouted to a remote check-in
facility near the 405 Freeway; Terminals 1, 2 and 3 would be
demolished; and parking garages in the center of the airport would
be knocked down to make way for a new central terminal.  An elevated
train would connect the check-in center, a consolidated rental car
facility and a transportation center near Aviation Boulevard and the
Century Freeway with the current facility.

The council will choose from among Hahn's vision and several expansion
plans proposed by his predecessor, Mayor Richard Riordan, or it could
decide to do nothing at all.

Hahn discarded Riordan's plans after the Sept. 11, 2001, terrorist
attacks.  He hoped to propose an LAX remodeling plan that everyone
could agree on, in part by trying to limit capacity at the facility
to 78 million passengers annually.

But a consensus has eluded the mayor.  Interests that he aggressively
courted during the planning phase, including most airlines at LAX and
residents in communities around the airport, now oppose his plan,
known as Alternative D.  These groups argue that environmental laws
do not preclude the mayor from changing his proposal.

"We believe the city has wide latitude in making modifications to
Alternative D," said Higgins, the airlines' representative.  "We
don't believe that modifications to Alternative D would require a new
environmental document and starting the procedure all over again."

Miscikowski said she believes officials can still meet environmental
requirements by drafting a compromise plan that draws on elements
studied and included in Riordan's and Hahn's proposals.

Changes can be made "as long as one created a hybrid of the good
things from within those plans, using some elements that are
consistent throughout," Miscikowski said.  "You can adopt a compromise
or drop things out, as long as you have a sense that the mitigation
measures are addressed in the document."

Miscikowski met with Rosenthal in Washington earlier this month and
discussed the mayor's plan for several hours.  The councilwoman has
also written a letter to City Atty. Rocky Delgadillo asking his office
for guidance on whether the council can ultimately change Hahn's plan.

"Will the council, as the actual certification authority for the
[environmental documents], have the ability, as we do in many land-use
cases, to recommend or request changes?" she wrote.

Delgadillo met with Miscikowski and agreed that the council could pick
and choose from projects in Riordan's and Hahn's plans as long as
those projects had adequate environmental analysis, said Eric Moses,
a spokesman for the city attorney.

Hahn's advisors disagree with Miscikowski's analysis and argue that
the mayor's LAX plan was carefully crafted to comply with stringent
state and federal environmental laws and to thwart legal challenges.

Those laws require a complex analysis of more than 50 topics, and a
mitigation plan that compensates for increased traffic, noise and
pollution that would result from overhauling the airport.  Any major
changes to the proposal could force officials to rework the analysis,
legal experts said.

In addition, airport officials say they cannot remove the plan's
centerpiece -- the ground transportation center at Manchester Square
-- because the facility is necessary to absorb increased traffic that
is expected to choke surface streets near the airport by 2015.

Hahn's plan would fail to comply with state and federal environmental
law if the facility were taken out of the proposal, said Jim Ritchie,
a deputy executive director at the city's airport agency.

"The plan is modeled around 60% of the vehicular traffic going into
and out of the ground transportation center," Ritchie said.  If it
"were taken out of the plan, the traffic analysis alone would send
us back to the drawing boards for at least another year."

Such a delay could doom the project, he said.  Hahn's plan is the 33rd
alternative developed by the airport agency over the last decade.  The
process ate up valuable time, leaving the agency only 11 years, under
Federal Aviation Administration guidelines, to secure approval and
build the project.  If officials are forced to return to the drawing
board they may have to kill the project altogether, Hahn's advisors
said.

With that in mind, experts and interested parties disagree about
what kinds of revisions city agencies can make without requiring the
airport agency and its consultants to redo the plan.

"The council really can do whatever they want when they approve the
project," said Sean Hecht, executive director of the UCLA
Environmental Law Center.  "The question is if whatever changes they
make in their project make the [environmental] document inadequate."

Exactly what council members are allowed to do with Hahn's plan
depends upon the interpretation of the word "significant," legal
experts agree.

"They can make changes that are not deemed significant," said Joel
Reynolds, a senior attorney at the Natural Resources Defense Council.
"It's not uncommon for changes to be made in a project that reduce or
downsize impacts and that would not in most cases require a revision
of the environmental documents."

Too large a change can invalidate the plans, however, as in the case
of the Playa Vista development, a dense mix of residential and
commercial projects north of LAX.  After phase two of that project
was downsized by 75%, officials had to rewrite all of the plan's
environmental documents, a process that required two years, said
Steve Sugarman, a spokesman for Playa Vista.

When the City Council reviews Hahn's LAX plan, it can interpret which
changes are "significant" by looking at air, traffic and noise
thresholds allowed by environmental law, attorneys say.  But figuring
out whether a change violates these standards takes time, they add.

"When you are going to change something over here, in order to make
sure that something doesn't pop up over there ... you just about have
to run a computer model," said Carlyle Hall, an attorney who advises
the city.  "That's not only expensive, but it takes time to set up
the model, to input it, then to run it and then to analyze it."

Airport officials have devised an ambitious schedule for Hahn's LAX
plan that would allow the agency to proceed with construction next
year, according to documents obtained by The Times.

Meeting these tentative deadlines is essential, proponents argue,
because the plan is running out of time.  To ensure that data used
to calculate the project's impact on the environment don't become
outdated, the FAA will require Los Angeles to finish construction by
the end of 2015, which is 20 years after work began on the airport
master plan.

To take advantage of the 11 years that remain, the Airport Commission
and the city's Planning Commission are scheduled to approve the
proposal by June 14, an airport agency timeline shows.  The county's
Airport Land Use Commission and the City Council are slated to sign
off by Sept. 14, and the city would receive final approval from the
FAA by Nov. 23, according to the schedule.

The FAA has promised to expedite its review of the mayor's plan and
has assigned additional staff to its Los Angeles office to help speed
environmental documents through the process, Ritchie said.  If city
officials change the plan significantly, this expedited review could
be canceled, setting the project back further, he added.

Project proponents argue that significant changes to Hahn's LAX plan
would not only endanger their timeline, but could also open the city
up to lawsuits that challenged the proposal's validity.

"When you get to the five-yard line," Hall said, "that's not where
you want to fumble the ball."

Tight timeline

City officials have devised an ambitious schedule for Mayor James
K. Hahn's $9-billion modernization plan for Los Angeles International
Airport. A few key dates in the tentative timeline:

*  April 28: The date the city has said it will release final
environmental documents.

* June 14: Deadline for Airport Commission and the city's Planning
Commission to approve the plan.

*  Sept. 14: Deadline for county Airport Land Use Commission and the
City Council to sign off.

*  Nov. 23: Deadline for the Federal Aviation Administration to
approve the plan.
--- End forwarded message ---