Dne 27. 09. 19 v 23:55 Kevin Fenzi napsal(a):
* Populate the new datacenter with new hardware to replace old hardware that
either wouldn’t survive the shipping or is due to be refreshed
In past, I was in touch with people working in datacenters and they moved several companies from one datacenter to
another one.
They claimed that during this transport there was non trivial number of servers which did not survive the shipping.
I do not recall the number. It may be worth to ask some people who done similar migration in past and get those numbers.
IIRC it was "small percent" (~1-2%).
And get pre-approved CAPEX for that. And some spare server as temporary replacement if something crucial dies.
--
Miroslav Suchy, RHCA
Red Hat, Associate Manager ABRT/Copr, #brno, #fedora-buildsys
_______________________________________________
infrastructure mailing list -- infrastructure@xxxxxxxxxxxxxxxxxxxxxxx
To unsubscribe send an email to infrastructure-leave@xxxxxxxxxxxxxxxxxxxxxxx
Fedora Code of Conduct: https://docs.fedoraproject.org/en-US/project/code-of-conduct/
List Guidelines: https://fedoraproject.org/wiki/Mailing_list_guidelines
List Archives: https://lists.fedoraproject.org/archives/list/infrastructure@xxxxxxxxxxxxxxxxxxxxxxx